Re: OFFICIAL - Main Street Streetcar Extension
This was literally all covered back when this district was formed. They even link to there own 2017 article within this article. I don't get why they are bringing this up again. (i mean, i know why...clicks. But honestly, it is a complete retread of stuff that was well publicized and discussed before the TDD was formed)
- normalthings
- Mark Twain Tower
- Posts: 8018
- Joined: Mon Mar 30, 2015 9:52 pm
Re: OFFICIAL - Main Street Streetcar Extension
They are trying to lay the groundwork for anti-E/W and NKC extension efforts. E/W is going to end up highly politicized.kboish wrote: ↑Fri Jan 14, 2022 2:44 pm This was literally all covered back when this district was formed. They even link to there own 2017 article within this article. I don't get why they are bringing this up again. (i mean, i know why...clicks. But honestly, it is a complete retread of stuff that was well publicized and discussed before the TDD was formed)
- Anthony_Hugo98
- Penntower
- Posts: 2008
- Joined: Fri Mar 22, 2019 10:50 pm
- Location: Overland Park, KS
Re: OFFICIAL - Main Street Streetcar Extension
I mean the news paper is dead, how else are they to generate ad revenue?normalthings wrote: ↑Fri Jan 14, 2022 4:06 pmThey are trying to lay the groundwork for anti-E/W and NKC extension efforts. E/W is going to end up highly politicized.kboish wrote: ↑Fri Jan 14, 2022 2:44 pm This was literally all covered back when this district was formed. They even link to there own 2017 article within this article. I don't get why they are bringing this up again. (i mean, i know why...clicks. But honestly, it is a complete retread of stuff that was well publicized and discussed before the TDD was formed)
- AlkaliAxel
- Broadway Square
- Posts: 2948
- Joined: Wed Jun 16, 2021 9:58 pm
- Location: West Plaza
Re: OFFICIAL - Main Street Streetcar Extension
Gonna be harder for them to make that case after Main St. extension.normalthings wrote: ↑Fri Jan 14, 2022 4:06 pmThey are trying to lay the groundwork for anti-E/W and NKC extension efforts. E/W is going to end up highly politicized.kboish wrote: ↑Fri Jan 14, 2022 2:44 pm This was literally all covered back when this district was formed. They even link to there own 2017 article within this article. I don't get why they are bringing this up again. (i mean, i know why...clicks. But honestly, it is a complete retread of stuff that was well publicized and discussed before the TDD was formed)
Their chance to kill the streetcar was back in 2014 before anyone knew how good it was, and when the haters could still make up imaginary world where the streetcar is a horrific thing.
It's like playing the Chiefs. Once the Chiefs get a lead...boy it's hard to come back and win the game at that point. You get one chance to stop it.
- DaveKCMO
- Ambassador
- Posts: 20072
- Joined: Sun Nov 27, 2005 6:22 pm
- Location: Crossroads
- Contact:
Re: OFFICIAL - Main Street Streetcar Extension
Doesn't really bother me the same story surfaced again because it reminds people who's paying and who's not, and that the whole thing is based on value capture and walkability. And it's not like there's anyone left at the Star who reported it in the first place.grovester wrote: ↑Fri Jan 14, 2022 1:12 pmYou nailed it.Highlander wrote: ↑Fri Jan 14, 2022 12:22 pm Anyone with a Star subscription want to summarize the article today: "Some of richest Kansas Citian's live in the street car zone. Why aren't they paying for it"? At the surface, it sounds like the typical create-controversy-where-there-isn't-any article that led me to drop my Star subscription.
I was disappointed by how many amplified it on social media.
- chrizow
- Global Moderator
- Posts: 17164
- Joined: Fri Aug 08, 2003 8:43 am
Re: OFFICIAL - Main Street Streetcar Extension
OMG extend it to Meyer, at least! I could be wrong but anecdotally it seems like there has been a lot of turnover in BKS north of 63rd (younger residents replacing older) so maybe it would be supported....not sure the tax capture would be sufficient since it's mostly single-family residences.
- DaveKCMO
- Ambassador
- Posts: 20072
- Joined: Sun Nov 27, 2005 6:22 pm
- Location: Crossroads
- Contact:
Re: OFFICIAL - Main Street Streetcar Extension
It's not. Already been looked at. But at least that's universal: You can't extend in any direction from river to UMKC without something broader to supplement the capital and operating cost. That said, I would expect value capture to continue playing a role (and generating the same level of controversy).
- Anthony_Hugo98
- Penntower
- Posts: 2008
- Joined: Fri Mar 22, 2019 10:50 pm
- Location: Overland Park, KS
Re: OFFICIAL - Main Street Streetcar Extension
How likely is it that a capital surplus exists from the TDD? Wasn’t that what helped KCSA to get the extra two streetcars from the initial segment? Or was it planned into the budget before then?DaveKCMO wrote: ↑Mon Jan 17, 2022 10:21 amIt's not. Already been looked at. But at least that's universal: You can't extend in any direction from river to UMKC without something broader to supplement the capital and operating cost. That said, I would expect value capture to continue playing a role (and generating the same level of controversy).
- normalthings
- Mark Twain Tower
- Posts: 8018
- Joined: Mon Mar 30, 2015 9:52 pm
Re: OFFICIAL - Main Street Streetcar Extension
On one hand, inflation will make the value of debt worth "less" quicker. On the other hand, on-going operations & maintenance for transit tend to outpace inflation. At current inflation rates, 2029 prices will be double today's.Anthony_Hugo98 wrote: ↑Mon Jan 17, 2022 10:58 amHow likely is it that a capital surplus exists from the TDD? Wasn’t that what helped KCSA to get the extra two streetcars from the initial segment? Or was it planned into the budget before then?DaveKCMO wrote: ↑Mon Jan 17, 2022 10:21 amIt's not. Already been looked at. But at least that's universal: You can't extend in any direction from river to UMKC without something broader to supplement the capital and operating cost. That said, I would expect value capture to continue playing a role (and generating the same level of controversy).
With the spike in SFH prices, I would be interested to see if the the funding gap for a south extension has narrowed at all once reassessment occurs. A cursory look at Zillow shows Zestimates (not always accurate) are up 2-3 times vs 2014. Is anyone familiar with the assessment process?
- im2kull
- Bryant Building
- Posts: 3982
- Joined: Tue May 24, 2005 4:33 pm
- Location: KCMO
Re: OFFICIAL - Main Street Streetcar Extension
2029 prices will be much, much higher because 1. Inflation in the US is greater than anyone wants to admit, and has been for the last few decades.. and 2. inflation is compounded. In fact, it's so bad that McDonalds created the "McDouble" in 2008 response to inflation. They decided to raise the price on a Double Cheeseburger from $1 to $1.35 (A 35% increase) but didn't want to leave the "Dollar Menu" void of a burger, so they created a Double Cheeseburger with one less slice of cheese and called it a "McDouble".. priced at $1. The cost of a McDouble has now risen to $3.36 in MO...above $5 elsewhere.normalthings wrote: ↑Mon Jan 17, 2022 4:39 pm At current inflation rates, 2029 prices will be double today's.
True inflation is tracked by the prices of the goods you purchase.. not the government sponsored BLS index. It's easy to see just how bad inflation is when considering those things and disregarding the BLS "statistics". A few good examples;
(In KCMO prices)
1. McDonalds Double Cheeseburger - 337% increase
2008 - $1
2022 - $4.37
2. McDonalds McDouble - 236% increase
2008 - $1
2022 - $3.36
3. McDonalds Apple Crisp - 473% increase
2008 - $0.40
2022 - $2.29
4. Autozone DLG 75 battery - 155% increase
2012 - $83
2022 - $212
5. Autozone DLG H8 battery - 150% increase
2012 - $93
2022 - $232
Considering that last year I was buying cans of chili beans for 3.5c/ounce, and this year they're 6.5c/ounce.. I'm guessing that by 2029 prices will have at least quadrupled.
- AlkaliAxel
- Broadway Square
- Posts: 2948
- Joined: Wed Jun 16, 2021 9:58 pm
- Location: West Plaza
Re: OFFICIAL - Main Street Streetcar Extension
Rag's gotten so boring this month we're discussing a can of beans
- normalthings
- Mark Twain Tower
- Posts: 8018
- Joined: Mon Mar 30, 2015 9:52 pm
Re: OFFICIAL - Main Street Streetcar Extension
Mainstreet Extension Updates:
- City will purchase 2 additional streetcars.
- Bond funding for project phase 2 decreased in part due to ARP grant
- Extra $3 million allotted for additional design services, no other info given
- Anthony_Hugo98
- Penntower
- Posts: 2008
- Joined: Fri Mar 22, 2019 10:50 pm
- Location: Overland Park, KS
Re: OFFICIAL - Main Street Streetcar Extension
Is this in addition to the # of streetcars that was initially slated for the extension? Or did the downsize the number of new cars they’re receiving?normalthings wrote: ↑Mon Jan 17, 2022 9:58 pm Mainstreet Extension Updates:
- City will purchase 2 additional streetcars.
- Bond funding for project phase 2 decreased in part due to ARP grant
- Extra $3 million allotted for additional design services, no other info given
- normalthings
- Mark Twain Tower
- Posts: 8018
- Joined: Mon Mar 30, 2015 9:52 pm
Re: OFFICIAL - Main Street Streetcar Extension
We will have 8 new streetcars coming instead of the 6 previously planned.Anthony_Hugo98 wrote: ↑Mon Jan 17, 2022 10:17 pmIs this in addition to the # of streetcars that was initially slated for the extension? Or did the downsize the number of new cars they’re receiving?normalthings wrote: ↑Mon Jan 17, 2022 9:58 pm Mainstreet Extension Updates:
- City will purchase 2 additional streetcars.
- Bond funding for project phase 2 decreased in part due to ARP grant
- Extra $3 million allotted for additional design services, no other info given
6 ordered + intend to exercise options for an additional 2. IRRC there are 10? total options. Funding for 2 more vehicles was assigned in an approved ordinance.
- Anthony_Hugo98
- Penntower
- Posts: 2008
- Joined: Fri Mar 22, 2019 10:50 pm
- Location: Overland Park, KS
Re: OFFICIAL - Main Street Streetcar Extension
Gotcha. Good to see KCSA has a positive outlook on ridership going forward, the numbers the last year made a long term ridership recovery seem shakiernormalthings wrote: ↑Mon Jan 17, 2022 10:17 pmWe will have 8 new streetcars coming instead of the 6 previously planned.Anthony_Hugo98 wrote: ↑Mon Jan 17, 2022 10:17 pmIs this in addition to the # of streetcars that was initially slated for the extension? Or did the downsize the number of new cars they’re receiving?normalthings wrote: ↑Mon Jan 17, 2022 9:58 pm Mainstreet Extension Updates:
- City will purchase 2 additional streetcars.
- Bond funding for project phase 2 decreased in part due to ARP grant
- Extra $3 million allotted for additional design services, no other info given
6 ordered + intend to exercise options for an additional 2. IRRC there are 10? total options. Funding for 2 more vehicles was assigned in an approved ordinance.
- normalthings
- Mark Twain Tower
- Posts: 8018
- Joined: Mon Mar 30, 2015 9:52 pm
Re: OFFICIAL - Main Street Streetcar Extension
We know that extending the River Front past the east edge was expected to require extra vehicles. If money exists under main street extension, use it to buy up vehicles making future extensions "cheaper."Anthony_Hugo98 wrote: ↑Mon Jan 17, 2022 10:22 pmGotcha. Good to see KCSA has a positive outlook on ridership going forward, the numbers the last year made a long term ridership recovery seem shakiernormalthings wrote: ↑Mon Jan 17, 2022 10:17 pmWe will have 8 new streetcars coming instead of the 6 previously planned.Anthony_Hugo98 wrote: ↑Mon Jan 17, 2022 10:17 pm
Is this in addition to the # of streetcars that was initially slated for the extension? Or did the downsize the number of new cars they’re receiving?
6 ordered + intend to exercise options for an additional 2. IRRC there are 10? total options. Funding for 2 more vehicles was assigned in an approved ordinance.
Last edited by normalthings on Mon Jan 17, 2022 11:01 pm, edited 3 times in total.
- Anthony_Hugo98
- Penntower
- Posts: 2008
- Joined: Fri Mar 22, 2019 10:50 pm
- Location: Overland Park, KS
Re: OFFICIAL - Main Street Streetcar Extension
Definitely changes the dynamic for expansion if you only need a couple SC for an expansion vs a whole set of 8-10normalthings wrote: ↑Mon Jan 17, 2022 10:29 pmWe know that extending the River Front past the east edge was expected to require extra vehicles. If money exists under main street extension, use it to buy up vehicles making future extensions "cheaper."Anthony_Hugo98 wrote: ↑Mon Jan 17, 2022 10:22 pmGotcha. Good to see KCSA has a positive outlook on ridership going forward, the numbers the last year made a long term ridership recovery seem shakiernormalthings wrote: ↑Mon Jan 17, 2022 10:17 pm
We will have 8 new streetcars coming instead of the 6 previously planned.
6 ordered + intend to exercise options for an additional 2. IRRC there are 10? total options. Funding for 2 more vehicles was assigned in an approved ordinance.
- beautyfromashes
- One Park Place
- Posts: 7298
- Joined: Mon Mar 21, 2005 11:04 am
Re: OFFICIAL - Main Street Streetcar Extension
I'm sure it's been talked about before, but with the new extension, what is the plan for when cars are broken down or a problem with one section of track? Will it stall out the whole system? Crossover track to go around? A much larger system will have more likelihood of disruption.
- normalthings
- Mark Twain Tower
- Posts: 8018
- Joined: Mon Mar 30, 2015 9:52 pm
Re: OFFICIAL - Main Street Streetcar Extension
IIRC, 2 cross over tracks. System designed so that a high frequency Union Station and North service can be run during events. I am not sure about running vehicles the "opposite way". I guess that is an advantage of dedicated center runningbeautyfromashes wrote: ↑Mon Jan 17, 2022 11:18 pm I'm sure it's been talked about before, but with the new extension, what is the plan for when cars are broken down or a problem with one section of track? Will it stall out the whole system? Crossover track to go around? A much larger system will have more likelihood of disruption.
NKC must be center running. East/West must be center running. Even if we never expand outside the core, center running is better.
Last edited by normalthings on Mon Jan 17, 2022 11:39 pm, edited 1 time in total.
- AlkaliAxel
- Broadway Square
- Posts: 2948
- Joined: Wed Jun 16, 2021 9:58 pm
- Location: West Plaza
Re: OFFICIAL - Main Street Streetcar Extension
Good. Huge actually.normalthings wrote: ↑Mon Jan 17, 2022 10:17 pmWe will have 8 new streetcars coming instead of the 6 previously planned.Anthony_Hugo98 wrote: ↑Mon Jan 17, 2022 10:17 pmIs this in addition to the # of streetcars that was initially slated for the extension? Or did the downsize the number of new cars they’re receiving?normalthings wrote: ↑Mon Jan 17, 2022 9:58 pm Mainstreet Extension Updates:
- City will purchase 2 additional streetcars.
- Bond funding for project phase 2 decreased in part due to ARP grant
- Extra $3 million allotted for additional design services, no other info given
6 ordered + intend to exercise options for an additional 2. IRRC there are 10? total options. Funding for 2 more vehicles was assigned in an approved ordinance.