Page 2 of 2

Re: 1531 Holmes

Posted: Wed Feb 14, 2024 11:00 pm
by Chris Stritzel
Eon Blue wrote: Wed Feb 14, 2024 10:49 am Is it really so hard to step down the elevation along Holmes and provide an active street level instead of blank walls?
Perfect spot for a customized art wall.

Re: 1531 Holmes

Posted: Tue Mar 05, 2024 2:32 pm
by Chris Stritzel
Per a post by Michael Collins on LinkedIn, this will be named “Mohawk at 15th”. Construction starts later this year.

Re: 1531 Holmes

Posted: Thu Mar 07, 2024 2:56 pm
by bspecht
Project will use the corner parking lot at 1534 Charlotte as resident parking, City offering a 10-year contract at $2,472/mo. https://clerk.kcmo.gov/LegislationDetai ... 7C&Search=

Re: 1531 Holmes

Posted: Sat Mar 23, 2024 11:52 am
by Chris Stritzel
Additional renderings were posted to Compass highlighting the retail and parking entrance on 16th as well as the parking entrance on Truman Road. I don't see any other changes made to the plan.

A public meeting was also held a few days ago. Per the meeting summary document uploaded to Compass, there were 8 attendees (4 neighborhood, 4 project team). Usual concerns were addressed (like parking and whether or not the alley would remain open - which it will). The anticipated start of construction is this August with a 16 month construction time frame, which means construction should wrap up around December 2025.
Image
Image
Image
Image
Image

Re: 1531 Holmes

Posted: Sun Mar 24, 2024 1:21 pm
by Eon Blue
Having a car hole on 16th instead of using the alley is disappointing.