Re: Proposed apartment for 14th and Grand - Two Light
2 permits issued on October 19
CiSI and CISM permits I do believe.
CiSI and CISM permits I do believe.
- normalthings
- Mark Twain Tower
- Posts: 8018
- Joined: Mon Mar 30, 2015 9:52 pm
Re: Proposed apartment for 14th and Grand - Two Light
Notes
Description Status Entered By Date
NOT IN GEN COMPLIANCE - MAKE CORRECTION DONE AB0713 16-Oct-2015
Land Development Division has reviewed the above referenced plans submitted for permit and made the following determination:
Plans are found to be "Not In General Compliance."
The following deficiency needs to be corrected:
1. Sheet C4.01 - Sanitary Sewer Capacity Analysis shall also include analysis of the downstream public main, inclusive of sanitary flows from all contributing upstream land use and the proposed building use, to verify there is adequate capacity within the existing sanitary sewer main to accommodate the proposed building use. Refer to APWA 5503 guidelines for estimating offsite flows.
Description Status Entered By Date
NOT IN GEN COMPLIANCE - MAKE CORRECTION DONE AB0713 16-Oct-2015
Land Development Division has reviewed the above referenced plans submitted for permit and made the following determination:
Plans are found to be "Not In General Compliance."
The following deficiency needs to be corrected:
1. Sheet C4.01 - Sanitary Sewer Capacity Analysis shall also include analysis of the downstream public main, inclusive of sanitary flows from all contributing upstream land use and the proposed building use, to verify there is adequate capacity within the existing sanitary sewer main to accommodate the proposed building use. Refer to APWA 5503 guidelines for estimating offsite flows.
- normalthings
- Mark Twain Tower
- Posts: 8018
- Joined: Mon Mar 30, 2015 9:52 pm
Re: Proposed apartment for 14th and Grand - Two Light
Results of Two Light Project Review. Project has to be revised.
- Eon Blue
- Alameda Tower
- Posts: 1127
- Joined: Mon Jan 30, 2012 11:28 pm
- Location: Downtown KCMO
Re: Proposed apartment for 14th and Grand - Two Light
Just tell tenants to space out their toilet flushes.
-
- Bryant Building
- Posts: 3850
- Joined: Fri Sep 16, 2005 12:12 pm
Re: Proposed apartment for 14th and Grand - Two Light
Was this determination for internal city use and follow up? Or, was this remark directed to the development team?ldai_phs wrote:Notes
Description Status Entered By Date
NOT IN GEN COMPLIANCE - MAKE CORRECTION DONE AB0713 16-Oct-2015
Land Development Division has reviewed the above referenced plans submitted for permit and made the following determination:
Plans are found to be "Not In General Compliance."
The following deficiency needs to be corrected:
1. Sheet C4.01 - Sanitary Sewer Capacity Analysis shall also include analysis of the downstream public main, inclusive of sanitary flows from all contributing upstream land use and the proposed building use, to verify there is adequate capacity within the existing sanitary sewer main to accommodate the proposed building use. Refer to APWA 5503 guidelines for estimating offsite flows.
- taxi
- Penntower
- Posts: 2111
- Joined: Thu Feb 08, 2007 12:32 am
- Location: S. Plaza
Re: Proposed apartment for 14th and Grand - Two Light
Those of us downstream from the P&L continue to get shit on.
-
- Bryant Building
- Posts: 3850
- Joined: Fri Sep 16, 2005 12:12 pm
Re: Proposed apartment for 14th and Grand - Two Light
Aren't you Stretching things a bit....?taxi wrote:Those of us downstream from the P&L continue to get shit on.
- normalthings
- Mark Twain Tower
- Posts: 8018
- Joined: Mon Mar 30, 2015 9:52 pm
Re: Proposed apartment for 14th and Grand - Two Light
This was directed to the development team(Hord Coplan Macht)loftguy wrote:ldai_phs wrote:Notes
Description Status Entered By Date
NOT IN GEN COMPLIANCE - MAKE CORRECTION DONE AB0713 16-Oct-2015
Land Development Division has reviewed the above referenced plans submitted for permit and made the following determination:
Plans are found to be "Not In General Compliance."
The following deficiency needs to be corrected:
1. Sheet C4.01 - Sanitary Sewer Capacity Analysis shall also include analysis of the downstream public main, inclusive of sanitary flows from all contributing upstream land use and the proposed building use, to verify there is adequate capacity within the existing sanitary sewer main to accommodate the proposed building use. Refer to APWA 5503 guidelines for estimating offsite flows.
Was this determination for internal city use and follow up? Or, was this remark directed to the development team?
-
- Administrator
- Posts: 11240
- Joined: Wed Feb 05, 2003 9:00 am
- Location: Historic Northeast
Re: Proposed apartment for 14th and Grand - Two Light
Kansas City is really turning into a kind of Hell's burgh.loftguy wrote:Aren't you Stretching things a bit....?taxi wrote:Those of us downstream from the P&L continue to get shit on.
-
- Bryant Building
- Posts: 3850
- Joined: Fri Sep 16, 2005 12:12 pm
Re: Proposed apartment for 14th and Grand - Two Light
Thanks Idai_phs.ldai_phs wrote:This was directed to the development team(Hord Coplan Macht)loftguy wrote:ldai_phs wrote:Notes
Description Status Entered By Date
NOT IN GEN COMPLIANCE - MAKE CORRECTION DONE AB0713 16-Oct-2015
Land Development Division has reviewed the above referenced plans submitted for permit and made the following determination:
Plans are found to be "Not In General Compliance."
The following deficiency needs to be corrected:
1. Sheet C4.01 - Sanitary Sewer Capacity Analysis shall also include analysis of the downstream public main, inclusive of sanitary flows from all contributing upstream land use and the proposed building use, to verify there is adequate capacity within the existing sanitary sewer main to accommodate the proposed building use. Refer to APWA 5503 guidelines for estimating offsite flows.
Was this determination for internal city use and follow up? Or, was this remark directed to the development team?
I would hope that the issuance of this kind of analysis to a development team is simultaneously being distributed to the Mayor, the City Manager and every member of city management...........for analysis of fact and solution. Otherwise, big city development has just come to a halt.
You can't call yourself a Smart City if you can't flush your toilet.
- KCDowntown
- Alameda Tower
- Posts: 1045
- Joined: Tue Oct 08, 2002 2:17 pm
Re: Proposed apartment for 14th and Grand - Two Light
This is not a big deal.
I've watched permits on Kiva for the better part of my 10+ years on this board. This sort of thing is common. The developers submit the plans, the city looks them over and comes back with their issues, the developers get their plans to comply and the permit gets issued.
Look over this permit for the P&L Building renovation.
Permits go back and forth with the city and developer all the time.
KCDowntown
I've watched permits on Kiva for the better part of my 10+ years on this board. This sort of thing is common. The developers submit the plans, the city looks them over and comes back with their issues, the developers get their plans to comply and the permit gets issued.
Look over this permit for the P&L Building renovation.
Permits go back and forth with the city and developer all the time.
KCDowntown
-
- Bryant Building
- Posts: 3850
- Joined: Fri Sep 16, 2005 12:12 pm
Re: Proposed apartment for 14th and Grand - Two Light
Obviously there is a back and forth on development details, but how can you say it's not a big deal that the main sewer lacks capacity to accommodate the development?KCDowntown wrote:This is not a big deal.
I've watched permits on Kiva for the better part of my 10+ years on this board. This sort of thing is common. The developers submit the plans, the city looks them over and comes back with their issues, the developers get their plans to comply and the permit gets issued.
Look over this permit for the P&L Building renovation.
Permits go back and forth with the city and developer all the time.
KCDowntown
-
- Alameda Tower
- Posts: 1008
- Joined: Sat Jun 20, 2009 12:58 am
- Location: Manhattan, Kansas
- Contact:
Re: Proposed apartment for 14th and Grand - Two Light
Except it's not saying that at all.
They simply forgot to do one of many tasks.The following deficiency needs to be corrected:
1. Sheet C4.01 - Sanitary Sewer Capacity Analysis shall also include analysis of the downstream public main, inclusive of sanitary flows from all contributing upstream land use and the proposed building use, to verify there is adequate capacity within the existing sanitary sewer main to accommodate the proposed building use. Refer to APWA 5503 guidelines for estimating offsite flows.
-
- Bryant Building
- Posts: 3850
- Joined: Fri Sep 16, 2005 12:12 pm
Re: Proposed apartment for 14th and Grand - Two Light
Ahhh. Ok. Thanks.longviewmo wrote:Except it's not saying that at all.
They simply forgot to do one of many tasks.The following deficiency needs to be corrected:
1. Sheet C4.01 - Sanitary Sewer Capacity Analysis shall also include analysis of the downstream public main, inclusive of sanitary flows from all contributing upstream land use and the proposed building use, to verify there is adequate capacity within the existing sanitary sewer main to accommodate the proposed building use. Refer to APWA 5503 guidelines for estimating offsite flows.
.....are you available to tag along and point out the obvious to me?
-
- Colonnade
- Posts: 748
- Joined: Thu Jan 29, 2015 11:31 am
Re: Proposed apartment for 14th and Grand - Two Light
How long could this delay the start of construction?
-
- Mark Twain Tower
- Posts: 9862
- Joined: Tue Jul 17, 2012 7:54 am
Re: Proposed apartment for 14th and Grand - Two Light
given there isn't a scheduled starting date and the project plan hasn't been approved yet,JBmidtown wrote:How long could this delay the start of construction?
the best estimate is somewhere from 0 days to permanently
- im2kull
- Bryant Building
- Posts: 3982
- Joined: Tue May 24, 2005 4:33 pm
- Location: KCMO
Re: Proposed apartment for 14th and Grand - Two Light
Loftguy.. The determination that the "main sewer lacks capacity" is not what that document states. It states that a routine development document needs to be prepared showing what the sewer loads of the new building are expected to be, and how that will contribute to the existing sewer mains. No big deal. Nobody's saying that anything is lacking capacity...loftguy wrote:Obviously there is a back and forth on development details, but how can you say it's not a big deal that the main sewer lacks capacity to accommodate the development?KCDowntown wrote:This is not a big deal.
I've watched permits on Kiva for the better part of my 10+ years on this board. This sort of thing is common. The developers submit the plans, the city looks them over and comes back with their issues, the developers get their plans to comply and the permit gets issued.
Look over this permit for the P&L Building renovation.
Permits go back and forth with the city and developer all the time.
KCDowntown
It's routine permitting work that should've already been done by the project team. It's so easy that anyone on this forum could do it, seriously. You find out the size of the main in the street, carrying capacity of that, usage of that, and how much additional usage the building adds. Boom done. The UPC lays all out all the figures for calculating sewer loads. Use it.
-
- Alameda Tower
- Posts: 1320
- Joined: Mon Oct 14, 2002 7:16 pm
- Location: Charlotte, NC
Re: Proposed apartment for 14th and Grand - Two Light
im2kull: Thank you.
-
- Bryant Building
- Posts: 3850
- Joined: Fri Sep 16, 2005 12:12 pm
Re: Proposed apartment for 14th and Grand - Two Light
I appreciate the extra explanation.
-
- Western Auto Lofts
- Posts: 552
- Joined: Wed Jan 11, 2012 10:00 am
Re: Proposed apartment for 14th and Grand - Two Light
For comparisons sake:
One Light
NEW/ADDN COMMRCIAL BUILDING PLANS REVIEW -- Feb 11 2014
Construction Barriers Went Up -- Mar 25 2014
Groundbreaking -- Apr 14 2014
First Move-Ins -- Nov 2015
Two Light
NEW/ADDN COMMRCIAL BUILDING PLANS REVIEW -- Oct 1 2015
IF the schedule was identical (I know it is not), the remaining timeline would look something like this:
Construction Barriers -- Mid Nov 2015
Groundbreaking -- Dec 2015
First Move-Ins -- July 2017
One Light
NEW/ADDN COMMRCIAL BUILDING PLANS REVIEW -- Feb 11 2014
Construction Barriers Went Up -- Mar 25 2014
Groundbreaking -- Apr 14 2014
First Move-Ins -- Nov 2015
Two Light
NEW/ADDN COMMRCIAL BUILDING PLANS REVIEW -- Oct 1 2015
IF the schedule was identical (I know it is not), the remaining timeline would look something like this:
Construction Barriers -- Mid Nov 2015
Groundbreaking -- Dec 2015
First Move-Ins -- July 2017