Re: Phase 2 streetcar to UMKC

Post by DaveKCMO »

Water/sewer work will be done first, rather than combined with track construction.
User avatar
beautyfromashes
One Park Place
One Park Place
Posts: 7189
Joined: Mon Mar 21, 2005 11:04 am

Re: Phase 2 streetcar to UMKC

Post by beautyfromashes »

Will the extension be launched in phases or all at one launch. For example, will they build and launch US to 39th St before the rest of the line to 51st St is built out? I know there is a turnaround set at 39th.
User avatar
KCPowercat
Ambassador
Posts: 33839
Joined: Mon Oct 07, 2002 12:49 pm
Location: Quality Hill
Contact:

Re: Phase 2 streetcar to UMKC

Post by KCPowercat »

My assumption has been one big shot.
User avatar
beautyfromashes
One Park Place
One Park Place
Posts: 7189
Joined: Mon Mar 21, 2005 11:04 am

Re: Phase 2 streetcar to UMKC

Post by beautyfromashes »

KCPowercat wrote: Tue Sep 15, 2020 7:50 am My assumption has been one big shot.
That’s the way the starter line was of course, but it was the starter line. The extension is also longer. It seems if half the new line has the track laid and a means to turn around you could get it open almost a year or more earlier than when all the track is finished.
User avatar
DaveKCMO
Ambassador
Posts: 20042
Joined: Sun Nov 27, 2005 6:22 pm
Location: Crossroads
Contact:

Re: Phase 2 streetcar to UMKC

Post by DaveKCMO »

KCPowercat wrote: Tue Sep 15, 2020 7:50 am My assumption has been one big shot.
Correct. The last items will be the connection to the existing track and catenary to avoid lengthy outages on the starter line.
User avatar
beautyfromashes
One Park Place
One Park Place
Posts: 7189
Joined: Mon Mar 21, 2005 11:04 am

Re: Phase 2 streetcar to UMKC

Post by beautyfromashes »

DaveKCMO wrote: Tue Sep 15, 2020 8:37 am
KCPowercat wrote: Tue Sep 15, 2020 7:50 am My assumption has been one big shot.
Correct. The last items will be the connection to the existing track and catenary to avoid lengthy outages on the starter line.
Thanks for the information.
User avatar
normalthings
Mark Twain Tower
Mark Twain Tower
Posts: 8018
Joined: Mon Mar 30, 2015 9:52 pm

Re: Phase 2 streetcar to UMKC

Post by normalthings »

flyingember
Mark Twain Tower
Mark Twain Tower
Posts: 9862
Joined: Tue Jul 17, 2012 7:54 am

Re: Phase 2 streetcar to UMKC

Post by flyingember »

User avatar
chaglang
Bryant Building
Bryant Building
Posts: 4132
Joined: Wed Jan 04, 2012 12:44 pm

Re: Phase 2 streetcar to UMKC

Post by chaglang »

normalthings wrote: Mon Sep 21, 2020 10:07 am CCROW transfer http://cityclerk.kcmo.org/liveweb/Docum ... 3SnolNLgPk
So as taxpayers we now have an ownership stake in Sherry DeJanes' fence.
User avatar
im2kull
Bryant Building
Bryant Building
Posts: 3926
Joined: Tue May 24, 2005 4:33 pm
Location: KCMO

Re: Phase 2 streetcar to UMKC

Post by im2kull »

chaglang wrote: Thu Sep 24, 2020 11:55 am
normalthings wrote: Mon Sep 21, 2020 10:07 am CCROW transfer http://cityclerk.kcmo.org/liveweb/Docum ... 3SnolNLgPk
So as taxpayers we now have an ownership stake in Sherry DeJanes' fence.
I'm not sure I'm following..?
flyingember
Mark Twain Tower
Mark Twain Tower
Posts: 9862
Joined: Tue Jul 17, 2012 7:54 am

Re: Phase 2 streetcar to UMKC

Post by flyingember »

im2kull wrote: Sun Sep 27, 2020 5:16 pm
chaglang wrote: Thu Sep 24, 2020 11:55 am
normalthings wrote: Mon Sep 21, 2020 10:07 am CCROW transfer http://cityclerk.kcmo.org/liveweb/Docum ... 3SnolNLgPk
So as taxpayers we now have an ownership stake in Sherry DeJanes' fence.
I'm not sure I'm following..?
You must have missed the lawsuit.
User avatar
DaveKCMO
Ambassador
Posts: 20042
Joined: Sun Nov 27, 2005 6:22 pm
Location: Crossroads
Contact:

Re: Phase 2 streetcar to UMKC

Post by DaveKCMO »

Despite how well it was covered during the streetcar elections, the lawsuit itself basically had no major coverage (especially the final ruling). The media has also not covered the transfer of the CCROW, which is unrelated to the lawsuit but would have merited a mention since the transfer is related to streetcar.
User avatar
Anthony_Hugo98
Valencia Place
Valencia Place
Posts: 1932
Joined: Fri Mar 22, 2019 10:50 pm
Location: Overland Park, KS

Re: Phase 2 streetcar to UMKC

Post by Anthony_Hugo98 »

DaveKCMO wrote: Mon Sep 28, 2020 10:19 am Despite how well it was covered during the streetcar elections, the lawsuit itself basically had no major coverage (especially the final ruling). The media has also not covered the transfer of the CCROW, which is unrelated to the lawsuit but would have merited a mention since the transfer is related to streetcar.
What significance does the transfer of the CCROW mean for the future?
User avatar
normalthings
Mark Twain Tower
Mark Twain Tower
Posts: 8018
Joined: Mon Mar 30, 2015 9:52 pm

Re: Phase 2 streetcar to UMKC

Post by normalthings »

Anthony_Hugo98 wrote: Mon Sep 28, 2020 11:32 am
DaveKCMO wrote: Mon Sep 28, 2020 10:19 am Despite how well it was covered during the streetcar elections, the lawsuit itself basically had no major coverage (especially the final ruling). The media has also not covered the transfer of the CCROW, which is unrelated to the lawsuit but would have merited a mention since the transfer is related to streetcar.
What significance does the transfer of the CCROW mean for the future?
Streetcar to UMKC runs in a northern section of the CCROW. It just means more progress towards getting Streetcar rolling to UMKC.
flyingember
Mark Twain Tower
Mark Twain Tower
Posts: 9862
Joined: Tue Jul 17, 2012 7:54 am

Re: Phase 2 streetcar to UMKC

Post by flyingember »

normalthings wrote: Mon Sep 28, 2020 12:01 pm
Streetcar to UMKC runs in a northern section of the CCROW. It just means more progress towards getting Streetcar rolling to UMKC.
For clarity, about 0.25 miles worth

It crosses the row at 47th and enters it at Volker
kcmiz
Pad site
Pad site
Posts: 59
Joined: Thu Jan 24, 2013 4:43 pm

Re: Phase 2 streetcar to UMKC

Post by kcmiz »

I know it doesn’t really affect this extension. But has she taken her fence down? What about the others who are encroaching on the CCROW?
User avatar
beautyfromashes
One Park Place
One Park Place
Posts: 7189
Joined: Mon Mar 21, 2005 11:04 am

Re: Phase 2 streetcar to UMKC

Post by beautyfromashes »

Now that federal money been received, doesn’t that kick off property taxes to start being collected according to the election? When will that start?
User avatar
normalthings
Mark Twain Tower
Mark Twain Tower
Posts: 8018
Joined: Mon Mar 30, 2015 9:52 pm

Re: Phase 2 streetcar to UMKC

Post by normalthings »

15 E 31st Street to be purchased by KCMO for the UMKC extension.

https://compasskc.kcmo.org/EnerGov_Prod ... b=moreinfo
User avatar
normalthings
Mark Twain Tower
Mark Twain Tower
Posts: 8018
Joined: Mon Mar 30, 2015 9:52 pm

Re: Phase 2 streetcar to UMKC

Post by normalthings »

The House has proposed $2.4 billion for CIG/New Starts projects that received funding in 2019 and 2020 (UMKC and Riverfront Extensions). The HEROES Act distributes the funds proportionally to qualified project sponsors and will not be counted toward the maximum federal financial assistance. It is my understanding that this means KC could receive the 50% Federal match + HEROES funds.

I estimate KC Streetcar to UMKC could receive around $35 million in bonus funds if enacted. Streetcar to Riverfront could get $10 million.

https://apta.com/advocacy-legislation-p ... t-funding/
flyingember
Mark Twain Tower
Mark Twain Tower
Posts: 9862
Joined: Tue Jul 17, 2012 7:54 am

Re: Phase 2 streetcar to UMKC

Post by flyingember »

What does that mean practically speaking if received?

More federal funding allowing for a smaller local tax?
Full funding sooner but just the asked for amount?
Extra money that can be used to do more, like better stops, a full crossover, or an extra train for more operations?